A new website

Dates from CSV, the part done drawn full, today marked.

1 The chart tag and its data gantt/website.pad pad
{chart 'gantt', label='task', from='begin', to='until', progress='done', mark='2026-03-20', title='A new website, done so far', width=640, height=320}
  task,begin,until,done
  Interviews,2026-01-12,2026-01-30,100
  Design,2026-01-26,2026-02-27,100
  Content,2026-02-16,2026-03-27,70
  Build,2026-02-23,2026-04-17,45
  Testing,2026-04-06,2026-04-30,0
  Launch,2026-05-01,2026-05-04,0
{/chart}
2 The result inline SVG · no JavaScript
A new website, done so far Interviews: Jan 12, 2026 – Jan 30, 2026, 100% done; Design: Jan 26, 2026 – Feb 27, 2026, 100% done; Content: Feb 16, 2026 – Mar 27, 2026, 70% done; Build: Feb 23, 2026 – Apr 17, 2026, 45% done; Testing: Apr 6, 2026 – Apr 30, 2026, 0% done; Launch: May 1, 2026 – May 4, 2026, 0% done Feb Mar Apr May Interviews Interviews: Jan 12, 2026 – Jan 30, 2026, 100% done Design Design: Jan 26, 2026 – Feb 27, 2026, 100% done Content Content: Feb 16, 2026 – Mar 27, 2026, 70% done Build Build: Feb 23, 2026 – Apr 17, 2026, 45% done Testing Testing: Apr 6, 2026 – Apr 30, 2026, 0% done Launch Launch: May 1, 2026 – May 4, 2026, 0% done Mar 20, 2026